Construction Progress · September 2026

From site preparation into structure.

NAYARI is now entering a new visible stage: the transition into the permanent basement structure.

15

Milestones completed

6

In the current transition

19

Milestones ahead

Current stage

Moving into basement structure.

With earthwork, building layout, water infrastructure and demolition completed, current work is focused on final cleanup, structural preparation and the start of basement columns.

Next visible change

The structure begins to rise.

Construction map

01–07Complete

Site & earthwork

08–15Complete

Infrastructure & demolition

16–21Now

Current structural transition

22–28Ahead

Underground structure

29–35Ahead

Main building structure

36–40Ahead

Finishes & completion

Full roadmap

40 milestones, from start to handover.

✓ Done● Now→ Ahead
01

Initial site survey & construction layout

✓
02

Site mobilization & working access

✓
03

Fauna relocation

✓
04

Initial site clearing

✓
05

Initial earthwork

✓
06

Building footprint & level setting

✓
07

Upper-site earthwork

✓
08

Main cistern excavation & base preparation

✓
09

252,000 L main cistern construction

✓
10

Cistern waterproofing & sealing

✓
11

Water-retention testing

✓
12

Cistern final approval

✓
13

Existing sales house cleared

✓
14

Selective dismantling & material recovery

✓
15

Existing structure demolition

✓
16

Final debris removal

~90%
●
17

Final site & soil preparation

~75%
●
18

Basement structural layout

~65%
●
19

Foundation & column starter preparation

~45%
●
20

Basement columns & vertical elements mobilization

~30%
●
21

Basement structural phase kickoff

~10%
●
22

Lower basement structure

→
23

Lower basement slabs

→
24

Upper basement columns & walls

→
25

Upper basement structure

→
26

Underground parking, storage & service areas

→
27

Ramps, stairs & circulation cores

→
28

Underground structure completion

→
29

Above-grade structural start

→
30

Lower residential levels

→
31

Middle residential levels

→
32

Upper residential levels

→
33

Rooftop structure & structural topping out

→
34

Main MEP rough-ins

→
35

Walls, façade, glazing & waterproofing

→
36

Interior partitions & finishes

→
37

Kitchens, bathrooms, millwork & fixtures

→
38

Amenities, pools & rooftop completion

→
39

Landscape, testing & commissioning

→
40

Final punch list, approvals & handover

→

Milestone count does not equal an official overall completion percentage. Percentages shown only on active activities are approximate phase-progress indicators and may be updated as construction advances.

Current update

September 2026

Demolition is now behind us. Final site cleanup is being completed as the project moves into preparation and structural work for the basement levels.

Completed

Initial site preparation, fauna relocation, earthwork, building layout, main cistern and demolition.

Now

Final debris removal, site preparation and the start of the first structural elements for the basement levels.

Next

Complete the underground structure, then continue into the main building structure.

Progress archive

Progress, month by month.

A concise archive of what happened on site, what was completed and what comes next.

September 2026

Demolition was completed and the site transitioned into final cleanup and preparation for underground structural work.

Current+
Demolition in progress at NAYARI
Mechanical demolition of the existing sales house using the excavator to clear the future building footprint.
Existing structure removal at NAYARI
Walls, slabs and remaining material from the existing structure being removed from the site.
Final site cleanup at NAYARI
Debris removal and final site clearing after demolition, preparing the work front for the basement structure.

Completed this period

Existing sales-house demolition completed and the main construction footprint cleared.

Moving into

Final debris removal, soil preparation and foundation/column starter work for the basement levels.

August 2026

The sales house was fully vacated and prepared for the transition into demolition.

View update +

During August, site preparation and the first visible structural elements advanced, including columns and work areas for the next stage.

Site preparation and structural work at NAYARI in August
Main cistern structure completed at this level, with column starters exposed and surrounding fill work underway.
Columns and vertical structure at NAYARI in August
Concrete columns and vertical reinforcement rising from the structural platform beside the cistern.
Construction progress and site preparation at NAYARI in August
Backfilling and grading around the completed cistern structure to prepare the site for the next construction stage.

Completed this period

Cistern structure and adjacent vertical elements advanced while surrounding grades were prepared.

Moving into

Sales-house clearance and selective dismantling ahead of demolition.

July 2026

Construction of the 252,000 L main cistern advanced through reinforcement, formwork and concrete work.

View update +

During July, concrete work, reinforcement steel and early structural preparation advanced alongside the infrastructure needed to continue clearing and preparing the site.

Foundation and reinforcement work at NAYARI in July
Reinforced-concrete slab and perimeter beams taking shape, with vertical column starters already in place.
Formwork and shoring at NAYARI in July
Interior formwork and shoring installed to support the cistern roof slab before concrete placement.
Workers installing reinforcement steel at NAYARI in July
Workers tying reinforcement steel for the cistern slab and beams ahead of the concrete pour.

Completed this period

Reinforcement, formwork and concrete work for the main cistern structure.

Moving into

Waterproofing, sealing and water-retention testing of the completed cistern.

June 2026

The structural slab advanced through full reinforcement, staged concrete placement and continued vertical starters.

View update +

During June, slab reinforcement was completed across this work front, concrete was placed progressively, and reinforcement starters were maintained for the vertical elements continuing into the next stage.

Reinforced slab and vertical starters at NAYARI in June
Slab reinforcement complete, with vertical starters integrated before concrete placement.
Structural slab concrete pour at NAYARI in June
Concrete placed in sections, then spread and leveled over the reinforced slab.
Completed concrete slab at NAYARI in June
Slab surface poured and leveled, with vertical reinforcement ready for the next structural work.

Completed this period

Reinforcement and progressive concrete placement of the structural slab in this work area.

Moving into

Continued columns, beams and structural work above the completed slab.

May 2026

Foundations began to take physical form through concrete pours, pedestals and column starters.

View update +

During May, foundation concrete pours and construction of pedestals and vertical starters advanced while localized excavation and preparation continued around the new structural elements.

Foundation pours and column starters at NAYARI in May
Concrete placement for footings and foundation pedestals with column starters already positioned.
Excavation and preparation between foundation elements at NAYARI in May
Excavation and level adjustment between foundation elements before the next concrete placements.
Foundation pedestals and vertical starters at NAYARI in May
Completed concrete pedestals with vertical reinforcement ready for continued column construction.

Completed this period

Foundation pours, structural pedestals and the first column starters.

Moving into

Continued columns, beams and foundation structure across the structural grid.

April 2026

Reinforcement work began for footings, foundation beams and vertical starters.

View update +

In April, the work front moved from excavation and grading into early structural reinforcement, with steel for footings, foundation beams and column starters while localized excavation continued to complete the foundation levels.

Footing and foundation reinforcement at NAYARI in April
Reinforcement steel assembled for footings and foundation beams along the first structural axes.
Rebar tying for beams and column starters at NAYARI
Reinforcement steel tied for foundation beams and column starters ahead of concrete placement.
Localized foundation excavation at NAYARI in April
Localized excavation and level adjustment to complete the remaining foundation points.

Completed this period

Initial reinforcement of footings, foundation beams and vertical starters.

Moving into

Foundation concrete placement and development of the first vertical structural elements.

March 2026

Earthwork intensified through slope cutting and formation of the main working platform.

View update +

During March, mass excavation, slope cutting and material removal advanced, expanding the work front and more clearly defining the project's initial levels and building footprint.

Excavation and material removal at NAYARI in March
Backhoe excavation and material loading to expand the working platform.
Slope cutting and terrain shaping at NAYARI in March
Slope cutting and terrain shaping along the property edge to reach project levels.
Expanded working platform at NAYARI in March
Work platform expanded following clearing, excavation and material removal.

Completed this period

Mass excavation, material removal and formation of the main working platform.

Moving into

Definition of foundation levels and preparation of footing locations.

February 2026

Construction access was established and initial clearing and grading began.

View update +

February marked the initial preparation of the work front: internal construction access was opened and graded for machinery, vegetation was cleared in intervention areas, and the first cuts and earthwork began.

Initial construction access established at NAYARI in February
Opening and grading of the internal access route to allow construction machinery to enter and circulate.
Initial clearing and earthwork at NAYARI in February
Initial clearing and cutting of the terrain to define the first circulation and work area.
Backhoe working on NAYARI construction access in February
Backhoe carrying out clearing, cutting and shaping of the initial construction access.

Completed this period

Site mobilization and initial construction access for machinery.

Moving into

Site clearing and initial earthwork.